Project Phasing
Work to be done by Hope and Development:
August 2009 – June 2010
-
Begin land acquisition process
-
Finalize the Artisan Village™ Master Plan
-
Begin networking with local government and potential NGO partners
-
Begin fundraising for first three phases of project development
-
Begin architectural planning and design process for IBACA
July 2010 – December 2010
-
Select vocational programs and begin vocational training
-
Build up vocational product market and begin sales to work teams
-
Finalize partner organization alliances and village plans
-
Begin work on necessary community infrastructure (water, roads, sewage)
-
Continue development of IBACA
January 2011 – June 2011
-
Continue Village infrastructure and Sports Complex
-
Begin construction on the Artisan Village buildings, market place, landscaping of Village, artisan workshops and coffee shop
-
Recruit community members
July 2011 – December 2011
-
Complete construction on Sports Complex Phase 1 and Artisan Village
-
Begin construction of town center, school, churches, health clinic and housing component
January 2012 – December 2012
-
Continue construction already in progress
-
Begin work on Agriculture training and Crop Co-op
January 2013 – December 2013
-
Complete Artisan Village™ Project